South Pars Gas Field Development - Phase 19

POGC assigned development of Phase 19 of the South Pars Gas Field to a consortium comprised of Petropars and the Iranian Offshore Engineering & Construction Company (IOEC), with Petropars Iran (PPI) as EPC contractor. Onshore facilities are located in Tombak (approximately 250 km southeast of Bushehr Port) at South Pars Site 2, while offshore facilities and wells are 120 km from the Persian Gulf coast. Offshore works include 21 wells and 4 platforms, two 32" pipelines for gas transfer (total 260 km), two 4.5" pipelines for MEG injection, and two 18" cladded pipelines for gas transfer from satellite platforms (12 km total). Final onshore production includes 50 MSCMPD of refined gas, 1.1 MT/year of LPG, 77,000 barrels/day of gas condensates, 1 MT/year of ethane gas, and 460 tonnes/day of granulated sulphur.


Sulfur / Sulphur Solidification & Forming (Granulation)
and Bulk Material Handling and Storage Unit
Capacity 720 tonnes per day
Method Sulfur / Sulphur Granulation
Client Ehsan J.V. (OD&CC, IGC, D&I)
Delivery Date 2011
Status Completed and in operation
Location Tehran - Iran
Feed Liquid sulphur from SRU plant
Product Granule (spherical shape) Sulfur / Sulphur
Number of Trains 2
Train Capacity 15 tonnes per hour / 360 tonnes per day
Storage 2 × 250 tonnes = 500 ton silo
Handling Rubber belt conveyor
Equipment
  • Granulator drum
  • Dry steam jacketed cyclone filter
  • Exhaust fan
  • Sulphur buffer tank
  • Liquid sulphur filter and pump group
  • Liquid sulphur transfer pump group
  • Rubber belt conveyor
  • Bucket elevator
  • Vibration screener
  • Sulphur re-melter package
  • Storage silo
  • Telescopic chute
  • Process water tank & pump group
  • Pre-fabricated piping and jacketed piping
  • UCP/PLC control system
  • Instrument
  • VFD panel

Our Work Experience