South Pars Gas Field Development - Phases 20 & 21

Phases 20 and 21 development was awarded to OIEC. These phases will produce 50 million cubic meters per day Natural Gas, 80,000 barrels per day Stabilized Condensate, 1 million tonnes per year LPG, 1 million tonnes per year Ethane Gas and 415 tonnes per day Sulphur.


Sulfur / Sulphur Solidification & Forming (Granulation)
and Bulk Material Handling and Storage Unit
Capacity 1,440 tonnes per day
Method Sulfur / Sulphur Granulation
Client Oil Industries' Engineering and Construction (OIEC)
Delivery Date 2017
Status Completed and in operation
Location Assaluyeh - Iran
Feed Liquid sulphur from SRU
Product Granule (spherical shape) Sulfur / Sulphur
Number of trains 4
Train capacity 15 tonnes per hour / 360 tonnes per day
Storage 2 X 1,100 tonnes = 2,200 ton silo
Handling Rubber belt conveyor and bucket elevator
Equipment
  • Granulator drum
  • Dry steam jacketed cyclone filter
  • Exhaust fan
  • Sulphur buffer pit
  • Liquid sulphur filter and pump group
  • Rubber belt conveyor
  • Bucket elevator
  • Vibration screener
  • Sulphur re-melter package
  • Storage silo
  • Telescopic chute
  • Process water tank & pump group
  • Pre-fabricated piping and jacketed piping
  • UCP/PLC control system
  • Instrument