Abadan Refinery Upgrading Project

National Iranian Oil Engineering and Construction Company (NIOEC) intends to construct a complete, safe and efficient new train of refinery inside the existing Abadan Refinery in the same plot area. This new refinery will process 210,000 BPSD of crude oil blend. The main design strategies of this project are maximizing Gasoline production, minimizing Fuel oil, and upgrading the refinery products specifications to meet requirements of Euro-V, with due consideration to the environmental and energy conservation measures, as well as economic aspects. Final products are gasoline, fuel oil, granular sulphur, etc.


Sulfur / Sulphur Solidification & Forming (Granulation)
and Bulk Material Handling and Storage Unit
Capacity 1,440 tonnes per day
Method Granulation
Client NIOEC/SEI & ODCC
Delivery Date 2022
Location Abadan - Iran
Feed Liquid sulphur from SRU plant
Product Granule (spherical shape) Sulfur/Sulphur
Number of trains 4
Train capacity 15 tonnes per hour / 360 tonnes per day
Equipment
  • Granulator drum
  • Dry steam jacketed cyclone filter
  • Steam jacketed exhaust fan
  • Sulphur buffer tank
  • Liquid sulphur filter and pump group
  • Process water tank & pump group
  • Pre-fabricated piping and jacketed piping
  • UCP/PLC and control system
  • Instrument
  • VFD and switchgear
  • Electrical (Lighting, Earthing and Cabling)
  • Firefighting and F&G system
  • Civil, shelter and steel structure
  • Pipe rack

Our Work Experience